|
 
Introduction
In 1895 The
Ottomans set the first water plant in Baghdad in a very
simple way, and during the British invasion period the
water distribution plants were small centers pumping
water from Tigris river directly through bad designed
and distributed main pipes full of residuals and weren’t
enough to meet the real need of water. At that time,
there were but two water high reservoirs one in Al-Karkh
and the other in Al-Rasafa and the water was distributed
to the residents of Baghdad alternately.
Information
Baghdad Water
Authority is one of Baghdad Mayoralty's affiliates. It
was founded as a corporation according to the water
distribution act no. (50) on 15, Dec., 1924, and its
administration linked to Works & Transportation
Ministry.
In 1931, law
no.(104) had been issued and in mid 1934 water
distributed to Al-Karkh & Rasafa districts for 24 hours
for the first time.
In 1955, law
no. ( 54) had been issued and according to which Baghdad
Water Authority had been founded and related
administratively to Interior Ministry, then related to
Municipalities Ministry when the latter had been founded
in 1959
Later many
amendments had been made according to act no. (39) in
1956, act no. (136) in 1963, act no. (163) in 1965, and
act no. (114) in 1970, according to which Baghdad water
Authority has become one of Baghdad Mayoralty's
affiliates. Many rules and instructions have been issued
recognizing the duty of Baghdad Water Authority.
In 1958, act
no. (107) has been issued concerned the Unified General
Balancing for the State in accordance with it BWA has
become a productive institute valued based on profit and
loss. According to this BWA began to plan and work on
the economic basis aiming to get profit without
affecting the citizens.
In June 1991,
BWA & Baghdad Sewer Authority have become one affiliate
according to act no. (17) on 10th,Jan., 1991.
This unification lasted for year and a half, as it was
cancelled according to act no. (9016) on 7th,
April, 1993.
On 5th,
Aug., 1995 act no. (16) has been issued according to all
the maintenance work of the water networks distributed
in residential mahalas was relegated to the
Municipality's offices. The cadre and the equipment of
these maintenance departments were moved to the
municipality offices according to the geographical area.
According to
the above act BWA work has been recognized to produce
water in its plants, transfer it through trunk pipes and
to maintain the water networks of more than (250)mm
diameters.
2- The
duty of BWA
Act no. (16)
has identified the duty of BWA according to article (8)
as follows:
BWA is
responsible of preparing the designs for water treatment
plants and implementing them, laying raw & treated water
networks, running, operating and supervising water
plants. It consists of the following departments:
First: Planning
& Following Up dep.
Second:
Implementing Projects dep.
Third:
Operation dep.
Fourth:
Mechanical dep.
Fifth: Quality
Control dep.
Sixth: Design
dep.
Seventh:
Computer dep.
Eighth :
Administration & Financial Affairs dep.
In addition to
the sections (Auditing, Warehouses, Law)
Note that the
article (17) of act no. (16) has identified the
Municipality's offices to maintain the water networks
except the trunk pipes.
Explanation
The
Municipality offices are responsible of distributing
water and maintaining the water sub-networks pipes (
250) mm and less in the residential mahalas, in addition
to maintaining all the raw & treated water pipes of
different sizes of the old networks till the these pipes
are cut and replaced with new trunk pipes.
Drinkable
Water
BWA produces
(2,250,000) m3 of drinkable water daily by eight water
treatment plants and sixty water Compact Units installed
in Baghdad's suburbs. The treated water is pumped to
eight ground reservoirs in order to be stored and then
it is re-pumped to the networks connected to these
reservoirs, whose capacity is ( 650,000) m3 distributed
in Baghdad's districts. In addition, there are nine
small Pumping Stations serve the house-complexes.
BWA has put its
plans according to the consulted studies prepared in
1982, that water production should be based on the daily
consumption average of the consumer ( 500) Liter/ day
taking into consideration the annual population
expansion. The plans have also included erecting
Al-Rasafa WTP with capacity of (2,250,000) M3/day
and installing sixteen reservoirs in both Al-Karkh &
Al-Rasafa banks, and trunk & main water networks, in
addition to renewing 140 old water networks and
constructing main & sub raw water networks for (150)
mahalas which don’t have raw water currently.
The delay of
executing Al-Rasafa WTP and its trunk pipes & reservoirs
increases the gap between the produced water quantities
and the real demand, which rises annually to be more
than one million m3/day of water. This explains the
treated water shortage especially in summer also the
current networks become very old.
aw Water
Baghdad city is
fed with raw water by five Raw Water Main Pumping
Stations whose total capacity about (3,456,000) m3/
day two of them in Al-Karkh district and the other three
in Al-Rasafa. These Stations pump raw water through new
network pipes cover the whole city. Howerver these
stations work with 40% of the their design capacity due
to not executing the green areas in Baghdad according to
the Pilot Design of the city and due to not
accomplishing some lines and distribution networks.
Under
Construction Projects
BWA has put
plans to construct projects in order to handle water
shortage problem according to the allocated amounts:
1-Executing
Sharq Dijlah First Expansion accomplished this year with
capacity of (225,000) m3/day which will tackle the water
shortage in Al-Rasafa district.
2- Preparing
the designs for Sharq Dijlah WTP Second Expansion with
the capacity of (225,000) m3/day.
3- During this
year, construction in water treatment plant with
capacity of (125,000) m3/day in Al-Sard City has been
commenced.
4- Installing
Water Compact Units (CU) in different areas as follows:
●Two CUs
of (9,000) m3/ day capacity have been installed with
executing the networks.
● A CU
of (200) m3/h capacity has been installed in
Orfally at US Donor's expense.
● Four
CUs of (50) m3/h capacity have been installed in Hai Al-
Tareq with executing 25 km of network at (APN)
organization's expense.
● A CU
of (25) m3/h capacity has been installed at Red Cross
Organization's expense in Al-Fahamah .
● A tank
of (50) m3/h has been installed at Red Cross
Organization's expense in Al-Suba'a .
●Two CUs
of (200) m3/h capacity with a network are being
installed in Al-Amary to get water to Al-Zahraa,
Al-Husseiniyah, and Al-Rashad districts at US Donor's
expense. Hoping it will be accomplished in the end of
October 2007.
● Plans
are prepared to supply and install 30 CUs each of (
4,500) m3 /day capacity in Oct., 2007 at Japanese
Donor's expense to be distributed them in Baghdad's
suburbs, 21 CUs in Al-Rasafa bank, while 9 CUs in
Al-Karkh bank.
●
Contracts have been signed to supply 5 CUs to be
received in Dec., 2007 and they will be installed in (
Bob-AlSham, Jaftlek { al-Rasafa}) and( Arab-Jbor in
Al-Dora { Al-Karkh}) districts within 2004 investment
plan.
5- Renewing
treated water networks for some mahalas according to the
allocated amounts have been accomplished, in addition
there are some projects to renew the networks are under
construction currently according to 2004 investment
Plan.
6- Commencing
construction in renewing treated water networks of all
the sectors &mahalas in Sadr City by PARSONS co.
7- Treated
water networks in new construction areas have been
executed according to the allocated amounts in addition
to some projects are being executed currently according
to 2004 investment plan.
8- Designs &
bill of quantities have been prepared to execute raw
water networks in some mahalas according to 2004
investment plan.
9- Contracts
have been awarded to fix the breaks of treated water
pipes by the Municipalities Offices due to lack of
vehicles & cadre and thus maintenance teams will be
ready to fix the breaks.
10- Some
projects of rehabilitating water treatment plants
(electrical, mechanical, and civil works) have been
accomplished, others are under construction, awarding,
and announcement according to allocated amounts
according to the 2004 investment plan.
11-
Implementing works to tackle the problem of water
shortage through making connections for enhancement
purposes and remove the blank flanges and replacing some
pipes that have many leaks by direct implementation by
BWA.
12- A central
lab will be erected for Laboratory Dep. in order to do
the chemical & bacteriological tests.
13- Some of
projects to handle the problem of water shortage and to
renew networks are included within 2005 investment plan.
14- In order to
handle water shortage problem, Al-Rasafa WTP, trunk
pipes, and ground reservoirs should be executed.
BWA's
Water Treatment Plants
|
Actual Capacity 1000m3/day
|
Plant's Name |
|
|
1150 |
Al-Karkh WTP |
1 |
|
500 |
9
Nissan WTP |
2 |
|
160 |
Al-Karamah WTP |
3 |
|
100 |
Al-Qadiyssiyah WTP |
4 |
|
100 |
Al-Dora WTP |
5 |
|
40 |
Al-Wathbah WTP |
6 |
|
50 |
Al-Wahdah WTP |
7 |
|
50 |
Al-Rasheed WTP |
8 |
BWA's
Reservoirs
|
Actual Capacity 1000m3/day |
Reservoir's name |
|
|
770 |
North Res. |
1 |
|
520 |
South Res. |
2 |
|
50 |
Abo-Ghraib Res. |
3 |
|
50 |
Al-Taji Res. |
4 |
|
5 |
Al-Rustomiyah Res. |
5 |
|
32 |
Al-Ameen Res. |
6 |
|
20 |
Al-Kamaliyah Res. |
7 |
|
34 |
Al-Obeidy Res. |
8 |
BWA's
Water CUs- Al-Karkh Bank
|
Actual Capacity m3/day |
CU's name |
|
|
4000 |
Shate'a Al-Taji 1 |
1 |
|
1280 |
Shate'a Al-Taji 2 |
2 |
|
2000 |
Shate'a Al-Taji 3 |
3 |
|
1000 |
Shate'a Al-Taji 4 |
4 |
|
3000 |
Um
Al-Asafeer |
5 |
|
2000 |
Old
Boaetha |
6 |
|
1000 |
New
Boaetha |
7 |
|
1280 |
Al-Makaseb 1 |
8 |
|
1280 |
Al-Makaseb 2 |
9 |
|
1000 |
Mandli |
10 |
|
1000 |
Al-Salam |
11 |
|
4000 |
Al-Salhiyah |
12 |
|
1000 |
Al-Akhaa |
13 |
|
1000 |
Al-Boamer |
14 |
|
1000 |
Abo
Reeshaa |
15 |
|
1000 |
Hussein Al-Safi |
16 |
|
300 |
Al-Ali |
17 |
|
1000 |
New
Dorah |
18 |
BWA's
Water CUs- Al-Rasafa Bank
|
Actual Capacity m3/day |
CU's name |
|
|
2400 |
Al-Nasr CUs |
1 |
|
2000 |
Old
Akad CUs |
2 |
|
8000 |
Tarq CUs |
3 |
|
8000 |
Al-Obour CUs |
4 |
|
4000 |
New
Akad CUs |
5 |
|
3000 |
Al-Amari CU |
6 |
|
1200 |
Orfaly CU |
7 |
|
24000 |
Abo- Nua'as CUs |
8 |
|
500 |
Al-Fahamah CU |
9 |
|
2000 |
Al-Muntather CU |
10 |
|
12000 |
Al-Kamaliyah CU |
11 |
|
24000 |
Al-Ameen CU |
12 |
BWA's
Pumping Station
|
Actual Capacity m3/day |
Station's name |
|
|
5000 |
Zayonah |
1 |
|
5700 |
Al-Habeebiyah |
2 |
|
3000 |
Al-Talibiyah |
3 |
|
1000 |
Tabet Al-Kurd |
4 |
|
19440 |
Al-Salihiyah |
5 |
|
26400 |
Al-Salam |
6 |
|
9600 |
Al-Saydiyah 6 |
7 |
|
3840 |
Al-Saydiyah 7 |
8 |
|
12000 |
Eskan Al-Dorah |
9 |
|
2000 |
Al-Kuwaity House Complex |
10 |
|
2000 |
Baghdad |
11 |
BWA's
Raw Water Pumping Stations
|
Actual Capacity m3/day |
Station's name |
|
|
32400 |
Al-Qanat RWPS |
1 |
|
32400 |
Al-Utaifiyah RWPS |
2 |
|
18000 |
Abo- Nua'as RWPS |
3 |
|
7200 |
Al-Zzafraniyah RWPS |
4 |
|
12960 |
Al-Kasrah RWPS |
5 |
|
12960 |
Al-Saydiyah RWPS |
6 |
|